A patio is the job where the format decides everything. Small pavers are a laying job; twenty-four inch slabs are a lifting job, and the two are planned differently from the first load of stone.

TYPICAL 300 SQ FT · 4 DAYS · BASE 8–10 T

The sequence

How the job actually runs

In order, with the tool each stage needs. Skip a stage and it comes back as the stage after it.

  1. 01

    Locates

    Free, legally required, five business days. A patio against the house sits over the services.

  2. 02

    Set the grade

    Slope away from the building, roughly an inch every eight feet. Decide it now; you cannot add it later.

  3. 03

    Dig out

    Six inches of base plus bedding plus the slab. Deeper if a hot tub is going on it — say so before you dig.

  4. 04

    Base in lifts

    Two lifts, compacted, checked with a level as you go. A flat base makes a flat patio; nothing later does.

  5. 05

    Bedding

    One inch screeded. On large format, use the bedding detail your supplier specifies — some slabs want an open-graded course, not sand.

  6. 06

    Set the slabs

    Big slabs go down once. Set them, tap them, and do not slide them — sliding drags the bedding out from under the edge.

  7. 07

    Cut and finish

    Cut wet, restrain the perimeter, sweep the joints. On large format the plate does not touch the surface at all.

How big, how long

The three sizes people ask for.

Day counts are for one or two people working at a homeowner’s pace, not a crew’s. Book the longer number.

Typical jobs

Typical sizes and how long to book
Bistro pad120 sq ft2 days
Dining patio300 sq ft4 days
Full entertaining area500 sq ft6 days

Tools this job uses

  • Toolcat
  • Plate compactor — ask us
  • Cut-off saw — ask us
  • Vacuum lifter — ask us

Anything marked “ask us” is a machine in the yard that is not on the rate card yet. Send the request with your dates and we will tell you what it costs before you commit to anything.

The planner

Your numbers, not an average

Tell it the size and it works out the material, the days and which machines you actually need — including the ones you do not.

Tell it about the job

Square feet. Length times width, near enough.

This is what decides the lifter, and usually it decides against it.

Access to the work
Who is doing it

What that takes

300 sq ft patio · 6 in base · two of you

SURFACE
300 sq ft

6 in of base. Walkways and patios. Four inches is the common minimum; six is the honest Simcoe number, because of freeze-thaw.

BASE
8–10 t

5.6 yd³ in the ground. Order the top of that range — what you order over what the hole measures — compaction, spillage and over-dig.

SPOIL
11 yd³

9.4 in of dig. Soil bulks when it is dug. The pile is always bigger than the hole. You will want a bin.

BEDDING
1 t

1 in screeded concrete sand. Screeded bedding sand. Thicker sand does not fix a low base — it becomes the low spot.

SURFACE ORDER
300 sq ft + 10%

Extra pavers for cuts and breakage. Five per cent on a plain rectangle, ten with curves.

COMPACTOR
1 day

2 lifts of 4 in. Maximum depth of one compaction lift. An eight-inch base is two lifts, not one pass.

SAW
0.25 day · 1 blade

About 42 lineal ft of cuts. Per 14-inch general-purpose segmented blade, cutting concrete pavers. Clay brick, granite and rebar cut this down hard.

LIFTER
worth it

About 67 lb a piece — a two-person carry. Alone, or a long carry from the driveway, take the lifter.

BOOK
4 days

Dig 1 · base 1 · lay 3 · cuts 0.25, less the overlap between them. Laying at 140 sq ft a day, two of you.

Check dates for the Toolcat

Estimates from average jobs — ground, grade and weather vary. When in doubt, book the extra day: it is cheaper than a second delivery. And order your stone before you book the machines.

The tools, and the ones you can skip

Tools for this job
ToolVerdictDays
Toolcat8 tonnes in and 11 yards out. That is the whole reason to have one on site.Needed2
Plate compactor2 lifts, four passes each. Compaction is never the bottleneck — spreading is.Not on the rate card yet — ask us and we will tell you what it costs and whether it is free.Needed1
Cut-off sawAbout 42 lineal ft of cuts, 1 blade. Cut wet.Not on the rate card yet — ask us and we will tell you what it costs and whether it is free.Needed0.25
Vacuum lifterAbout 67 lb a piece — a two-person carry. Alone, or a long carry from the driveway, take the lifter.Not on the rate card yet — ask us and we will tell you what it costs and whether it is free.Worth it2

From experience

What people get wrong

  • Sand-setting large-format slabs like small pavers.

    Follow the supplier's bedding detail. Large format on plain sand rocks within a season.

  • Running the plate over finished slabs.

    Protective pad on regular pavers; on slabs over about eighteen inches, no plate at all.

  • Two people walking a heavy slab into place.

    Over about a hundred pounds a piece, two people is not the answer. That is the lifter's job.

  • No fall away from the house.

    About an inch every eight feet. A flat patio is a puddle with furniture on it.

  • Sliding slabs to line them up.

    Lift and reset. Sliding ploughs the bedding and leaves a hollow corner.

Before you dig

The parts that are not optional

One sentence and one link each. We rent machines — we do not read by-laws for you, and none of this is legal or engineering advice.

  • Book your locates first. Free, and it is the law.

    Ontario One Call is free, and a locate is legally required before you dig. Submit the request at least five business days before you plan to start — infrastructure owners have five business days for a single address, and there is no guarantee they use fewer. Book it the day you decide to do the job, not the day the machine lands.

    Ontario One Call — locate requests for homeowners
  • Cut wet, or split instead of sawing.

    Cutting concrete pavers dry throws respirable crystalline silica, which Ontario regulates under O. Reg. 833. The control is water suppression or a process that makes less dust — splitting rather than sawing is explicitly the safer route. A paper dust mask is not respiratory protection.

    Government of Ontario — silica on construction projects: legal requirements (O. Reg. 833)
  • A protective pad before the plate touches finished pavers.

    Running a plate compactor straight onto a laid surface chips corners and cracks faces, and on large-format slabs it does it on the first pass. Use the roller pad or the rubber mat, every time. On slabs over about 18 inches, do not run the plate at all.

Be clear about this

What we do not supply

The machines move material around your site. They do not haul it to the curb and they do not bring it in. Sort this out before you book anything.

  • Aggregate deliveryGranular A and concrete sand come from a pit, by the tandem load. We rent the machine that spreads it, not the truck that brings it.
  • Spoil removalA bin, or a dump trailer from somebody who has one. The Toolcat moves the pile around your site; it does not take it away.
  • Pavers, slabs and blockFrom your supplier, with the cut allowance added.
  • GeotextileOver clay, it is the difference between a base that lasts and one that pumps mud into itself.
  • Edge restraint and spikesWithout it the field creeps and the first spring shows you where.
  • Polymeric sandAnd the patience to sweep it in dry.
  • Hand toolsScreed rails, string line, level, rubber mallet, knee pads. Bring your own.

Questions

The ones we get asked

How heavy is a 24 × 24 slab?

Concrete runs about 2,400 kg per cubic metre, which works out to roughly 0.087 lb per cubic inch. A 24 × 24 × 2⅜ slab is therefore about 118 lb, and a 24 × 36 is about 178 lb. Both are past the point where two people is a good plan.

When do I need a vacuum lifter?

Over about fifty-five pounds a piece it is worth it; over about a hundred it is the answer. Under that — a 4 × 8 paver, a 12 × 12 slab — you do not need it, and we will say so.

How deep should a patio base be?

Four to six inches for foot traffic, and six is the number we would use here. A hot tub or a vehicle changes it to a driveway spec.

Can I compact the surface at the end?

On regular pavers, yes, over a protective pad. On large-format slabs, no. The plate finds the unsupported corner and takes it off.

Showing our work

Where these numbers come from.

Anything marked [VERIFY] is trade convention we have not yet put in front of a supplier. It is good enough to plan against and we would rather say so than dress it up.

Next

Related guides, and where we work

  1. Laying an interlock driveway

    The base is the job. The pavers are the part everyone photographs, and they are two of the seven days — get the eight inches under them right and the driveway outlives the house. Read the guide

  2. Rebuilding precast steps

    This is the job with the highest injury and breakage risk on the whole list, and it is short. A precast step is five or six hundred pounds of concrete that has to land within a quarter inch of where you want it, once. Read the guide

  3. Renting in Barrie

    Inside the flat-rate delivery core — one trip covers drop-off and pickup. Equipment in Barrie

  4. Renting in Innisfil

    Inside the flat-rate delivery core — one trip covers drop-off and pickup. Equipment in Innisfil

Tell us the dates. We will confirm by text.

Pick the machines, send the request, and we will handle the hauling.